Indian diesel-electric submarine "Sindukirti" launched in India
The multi-year saga of repair and modernization of diesel-electric submarines "Sindukirti 'in Visakhapatnam, India was an important event - the ship was launched. Serious participation in the preparation of the descent took a group of Russian experts, including representatives of "Sprockets".
Before launching
In early November, a group of factory workers returned to Severodvinsk, and to replace them went to another team. According to Deputy Chief of 7 Mikhail Blinov, the past trip was different special tensions, not only in the working points.
Our compatriots had to witness the devastating hurricanes that swept over Visakhapatnam on October 12, paralyzing life in the city and the shipyard where our countrymen were involved.
- Due to the fact that the city's infrastructure was destroyed, a huge city remained without electricity, as well as a shipyard. As a result, our work has been disrupted for a week. But we must pay tribute to the leadership «Hindustan Shipyard Ltd.» - in the shortest possible time was provided back-up electricity supply line, and work resumed on the order, - said Mikhail Blinov.
Another misfortune for group travelers became malaria, had never bothered. This time she did not remain indifferent to the "guests" - a group of many sick, and four of the returnees dolechivatsya already here. Now a dangerous disease are seriously - take all the necessary preparations for the prevention.
Haste and close attention to the course of the repair ship, according responsible for providing a conclusion ordering felt throughout a three-month trip. Even though forced because of Hurricane simple, the Indian military is not rescheduled launching the boat. However, maintaining the title of Russian shipbuilder, our specialists have coped with their work without disrupting the schedule obgovorёnnye general terms.
All October had to work overtime. At the same time from a group of one hundred two people (that is how much the Russians are involved in the repair of "Sindukirti") more than thirty again brought on board instead of resting in their spare time. To their credit - all sympathetic to the problem and in a very short time completed all activities on repair and preparation of order to be launched.
A lot had to do. Closed-built huge amount of documents. Before descending order over water installation and commissioning of equipment complexes "Pyrite-M" and "Palladium-M", responsible for the operation of the steering group and the ship's systems. Particularly helped in setting up a mechanic shop 10 AN Elenskiy. Presented to the customer mounted navigation system "Appassionata-EKM.1" and combat system AIUS "Lama-CME" modernized missile complex «Club-S» - the main weapon of the boat, completed work on a range of mine-torpedo weapons. I would also like to acknowledge the work of specialists "Arctic", namely VA Kulebakin SA Drochneva, RA Schilina, RF Patrakeeva, AS Borovik, AV Kruglov, AS Ershov, RG Smirnov.
Such large amounts reserved for the Russians, due to the fact that the Indians do not have much experience in setting up and repair complexes Russian submarines. Hence the numerous failures in the course of work, delays with various activities for repair and modernization. Sometimes they numbered two months, significantly delayed the general course of recovery "Sindukirti."
- "Thanks" this attitude is the same setting hydraulics and electrics complex "Palladium-M" cost us two weeks of hard work instead of the one and a half months at a normal pace, - says Mikhail Blinov.
On the eve of entering the open water in a three-shift operation had to contend with another difficulty - pripilovkoy tracks torpedo - stricter requirements to comply with the geometry forced to work hard for two weeks (RY showed their skills Perminin, Shuleva AA, VV SEMYANNIKOV from the shop 10).
Plus delays were added numerous consultations of our designers and engineers who are assisted by their Indian colleagues work.
Ahead of the ship's mooring stage trials that Russian experts "Sprockets", "Arctic" and "Aurora" hold together with the project manager Andrei Frolov. Andrew F. was at the forefront of repair "Sindukirti" and to this day continues started more than eight years ago the matter. Problematic issues to be addressed in Russia are controlled by the head of the department Andrei Nevenkina 7, so that in the distant Indian professionals do not feel neglected and deprived.
It should be noted that during this time the approach of the Indian side to repair the ship has changed for the better. They increased the number and level of experts on the order, the military almost daily appealed for help to the Russians up to solve some problems of its own.
The reluctance of the customer to postpone the execution of works at Russian breakdowns own terms inconvenience, but the years of experience that have gained shipbuilders in the repair of five Indian orders, undoubtedly helped.
- This is especially felt the last month and a half trip, - says Mikhail Blinov - Contact us became closer, canceled checks weekly, they were replaced daily, allowing more quickly to solve all problems.
Relax is not necessary - in the plans of the Indian side to finish mooring trials by the end of March 2015, so ahead of the Russians a few months of hard work in the hot sun of India.
Based on materials from the publication "North week."