Looking at the low quality photo, 003 is at bow completion stage. Going back to 002 photo that appear to be around june-july of 2016. Lets say 003 is at around june 2016 stage of 002.

According to the timeline from
Please, Log in or Register to view URLs content!

Stages arounded to nearest start of month and time from june 2016 was:
Launch May 2017 +11 month
Start of sea trials May 2018 + 12 month
Commision Jan 2020 + 19month.
Total 3.5year.

Looks like I have under counted sea trial period by about half a year. More likely timeline: 1 year till launch, 2 year till sea trial, 4 year till commission at end of 2025.
I am expecting the testing and fixing of EMALS will take a long time, I won't be surprised if it is one or even two years long.
 