Electrical & Mechanical Equipment Installed at
Hydro Power Project by German Firm Voith Hydro E&M Contractor.
1410 MW Tarbela 4th Extension HydroPower Project Under construction Tarbela 4th will be commissioned by this month with its first unit going into operation.
while the second unit of the project will come on line by end April 2018 and the third unit by end May 2018.
Under Tarbela 4th Extension Hydro power Project, 3 electric power generating units - each of them having capacity of 470 MW-are being installed at tunnel 4 of Tarbela Dam.
With completion of the project, generation capacity of the existing Tarbela Hydel Power Station will increase to 4888 MW from the existing 3478MW. Tarbela 4th Extension Hydro power Project will provide 3840 Giga Watt H(3.84 billion units of electricity)to the National Grid annually..